Actions
Bugs #53
openProcess Recalculate Condition not exist meter reading
Start date:
04/15/2025
Due date:
04/15/2025 (14 days late)
% Done:
0%
Estimated time:
Story Point:
0.00
Sprint:
Description
Please refinement proccess on backlog recalculate¶
If meter type not in (SC and SD) and bhp_meter_reading not exist
then not process create bhp_pm
if meter type not in (SC and SD) and bhp_meter_reading is exist ( get BHP_MeterReading where DocumentDate <= date as of on process backlog recalculate )
then not process create bhp_pm and prosess get value bhp_pm same as coding exist
else meter type in (SC and SD), running process existing
Actions